The complexity of chemical and process plants in consideration of environmental and safety standards, cost pressure and adherence to schedules are challenges that are met by our team successfully.

Pharmaceutics / Life Science

As a qualified partner, we are familiar with all necessary trades of the project. We provide our services in consideration of all applicable rules and regulations. Our specialists are familiar with the GMP rules and standards.

Oil / Gas / Energy

We support you in building new plants as well as optimizing and extending existing ones. We take the sector's characteristics into account and incorporate our long-term project experience.

Solar / Semiconductors

The supervision and support of technology-intensive projects represent a complex task. Thus they are closely coordinated with our clients. By combining your core competences with our project experience we make sure to achieve project success.

Feasibility Study / Basic Engineering Polymer Technology for Chemical Enhanced Oil Recovery

Basic engineering, including a site evaluation, for the construction of a new plant to manufacture polymers for oil production. The sites under consideration were San Giorgio in Italy and Botlek in the Netherlands.

Task

Preparation of a feasibility study with subsequent basic engineering (+- 10% cost estimation) for a polymer plant. Two existing sites were analyzed partially with on-site surveys.

During the on-site surveys, corresponding tie-in points for existing utilities were clarified and labeled together with the operator in order to guarantee a subsequent switch-over without an interruption of normal operation.

In addition to profitability calculations done by the client, possible future expandability was also taken into account.

Challenges

Protection of the existing facilities during an expansion as well as the changed seismic classification in Italy had to be taken into consideration.

Simultaneously further expansion projects were being realized on site, which required close coordination with regards to available resources.

Project Result

Reliable +-10% cost estimation with risk assessment as a guideline for the location decision made by the client's senior management.

Construction of a HN03 and Highly Concentrated Nitric Acid Unit for BASF Ludwigshafen


Task

This order contained planning, material procurement, turnkey delivery and commissioning of a HN03, NH3 and highly concentrated Sulfuric Acid unit.

These units were built within the scope of the new TDl plant (300,000 t/a; investment EURO 1,000m) at the Ludwigshafen location.

Besides contract/claim management, EPMC was responsible for HSE and E/I&C construction management on behalf of M+W Group.

Projekt Result

On-time completion to ensure timely integration into the TDI plant in line with the budgeted cost.

EPMC

We are a small-scale enterprise that – together with and for you – leads your projects to success.

We will help you to manage, design and tender your projects with the aim to and achieve our most important objective together with you: The successful execution of your projects.

Contakt

Gewerbepark Lindach A 1a

84489 Burghausen


+49 8677 8736236

info@epmc-gmbh.de

Copyright © EPMC 2026 - all rights reserved · Legal Notice ·Data Privacy